Free Construction BOQ Sample (With 1200 Sq Ft House Example)

When planning a residential building, cost discussions often begin with a per square foot rate. While that number provides a broad budget estimate, it does not explain how quantities are distributed across excavation, RCC, brickwork, plaster, flooring, or utilities like plumbing and electricals.

A construction BOQ helps bridge that gap.

A construction BOQ (Bill of Quantities) is a document that lists all measurable work items in a project along with their quantities, units, and rates. It is used for cost estimation, contractor comparison, and budgeting before construction begins. In most residential projects, it forms the base document for quotation evaluation.

For independent house construction, a properly structured BOQ brings clarity to both scope and budget. 

This article explains how a residential BOQ is structured and how you can use a sample format to understand construction quantities more clearly.

In this guide, we explain:

  • What a construction BOQ includes
  • How a residential BOQ is structured
  • A worked quantity example for a 1200 sq ft house
  • How to download a sample BOQ format
  • Where to access an editable BOQ format in Excel

If you want a broader understanding of current pricing trends, you may also review our detailed guide on construction cost per sq ft in India, which explains how overall rates are derived before breaking them into BOQ components

What Is a Construction BOQ?

A construction BOQ is a detailed schedule of measurable work items in a building project. Each item is defined with:

  • Description of work
  • Unit of measurement (Cu.m, Sq ft, Kg, Nos, L.S)
  • Quantity
  • Rate
  • Amount

In residential construction, the BOQ typically follows the sequence of execution, starting from site preparation and foundation, moving through structural works, and concluding with finishes and services.

Unlike a rough estimate, a BOQ does not rely on a single cost figure. It distributes the project into measurable components. This structure makes cost analysis and contractor comparison more reliable.

What Is Included in a Construction BOQ?

A residential construction BOQ generally includes substructure works (excavation and PCC), RCC structural works, masonry, plaster, flooring, doors and windows, plumbing, electrical works, and contingency provisions.

The real value of a BOQ becomes clearer when you see how it influences cost control on site.

Why a Residential BOQ Matters in House Construction

In small residential projects, cost variation usually arises from unclear quantities of materials.

If the excavation depth is not measured correctly, earthwork increases.
If the slab thickness is not defined, the RCC quantity changes.
If wall areas are not calculated properly, plaster and paint costs escalate.

A BOQ converts drawings and assumptions into measurable quantities. This provides:

  • A consistent basis for contractor quotations
  • Visibility into material consumption
  • Clear scope definition before work begins
  • A reference for stage-wise billing

In independent house construction, the BOQ often becomes the working reference during execution.

Typical Structure of a Residential Construction BOQ

A residential BOQ is usually divided into logical work categories. The structure below reflects common practice in independent house construction.

1. Site & Substructure Works

These include initial groundwork and foundation-related items:

  • Site clearance and layout marking
  • Excavation for the foundation
  • Backfilling with soil
  • PCC below the footing

These items are measured primarily in cubic metres (Cu.m).

2. RCC Structural Works

This section forms the structural framework of the building:

  • RCC in footings
  • RCC in columns
  • RCC in slab
  • Centring and shuttering
  • TMT steel reinforcement

Quantities are measured in cubic metres (RCC), square metres (shuttering), and kilograms (steel).

The structural portion of a house typically forms a major share of the total cost. For a deeper breakdown, you can refer to our guide on RCC slab labour cost.

3. Masonry & Plaster

After structural works, masonry and surface finishing begin:

  • Brickwork
  • Internal plaster
  • External plaster
  • Ceiling plaster

These are measured in cubic metres (brickwork) and square feet or square metres (plaster).

4. Flooring & Finishes

This section includes floor and surface finishes:

  • Vitrified flooring
  • Skirting
  • Waterproofing (toilets and roof areas)

Measured primarily in square feet or running metres.

5. Doors & Windows

Openings are defined separately to ensure clarity in count and specification:

  • Main door
  • Internal doors
  • Aluminium windows

Measured in numbers (Nos) or square feet (for window area).

6. Services

Services are typically represented as composite or lump-sum items, depending on the detailing level:

  • Plumbing (complete house)
  • Septic tank
  • Electrical (complete house)

In more advanced BOQs, plumbing may be split into piping and fixture components.

Sample Quantity Framework for a 1200 Sq Ft House

To understand how quantities are derived, let us look at a simplified example.

Consider a ground-floor house of approximately 1200 sq ft built-up area with:

  • 3 bedrooms
  • 2 toilets
  • 1 kitchen
  • RCC framed structure

Using standard residential thumb rules, quantities may be estimated as follows:

  • RCC quantity based on the built-up area factor
  • Steel calculated per cubic metre of RCC
  • Brickwork derived from the wall volume factor
  • Plaster is calculated as a multiplier of the built-up area
  • Window area based on the number of windows x average size
  • Plumbing cost scaled by area plus toilet fixtures

These quantities form the backbone of the BOQ. Rates are then applied to calculate the total project cost.

At the bottom of the BOQ, the following are typically added:

  • Subtotal
  • Contingency (commonly 5%)
  • Final project cost
  • Cost per square foot

This structured breakdown provides a more reliable cost framework than a single lump-sum estimate.

What Does a Construction BOQ Format in Excel Look Like?

A standard BOQ format in Excel contains the following columns:

| Sl No | Description | Unit | Quantity | Rate | Amount |

The quantity column may be:

  • Manually entered (basic format), or
  • Auto-calculated based on built-up area and layout inputs (advanced format).

An advanced residential BOQ model may allow users to configure:

  • Built-up area
  • Number of bedrooms
  • Number of toilets
  • Internal door count
  • Window count

Quantities update automatically, and the cost per square foot adjusts accordingly.

This makes it easier to test different scenarios, such as increasing the built-up area or adding a toilet, to see how the cost changes.

Download Free Construction BOQ Sample PDF (Bill of Quantities format)

To illustrate the structure clearly, we have prepared a sample BOQ for a 1200 sq ft residential house.

The sample includes:

  • 22 detailed BOQ line items
  • Standard residential work categories
  • Sample quantities based on thumb rules
  • Sample mid-range market rates
  • Final cost calculation

You can download the free construction bill of quantities sample PDF below and review the format.

Free Construction BOQ Sample 1200 SqFt

Editable Construction BOQ Format in Excel

For users who want flexibility beyond a static sample, an editable BOQ format in Excel is more practical.

An advanced Excel version typically includes:

  • Configurable built-up area
  • Layout-aware inputs (doors, windows, toilets)
  • Hybrid service costing (area + fixtures)
  • Automatic contingency calculation
  • Cost breakdown summary
  • Rate sensitivity analysis (steel and cement impact)

Such a model is useful for:

  • Comparing contractor quotes
  • Planning a budget before construction
  • Understanding material price impact
  • Preparing preliminary cost estimates

[ Get Editable Construction BOQ Excel Template – ₹299 ]

Common Practical FAQs

Q. Who prepares a construction BOQ for a house?

In residential projects, a BOQ is usually prepared by an architect, quantity surveyor, or civil engineer based on drawings and design specifications.

Q. Is a BOQ mandatory for small residential houses?

A BOQ is not legally mandatory for most small houses, but it is recommended to ensure clear scope definition and avoid cost disputes.

Q. How accurate is a thumb-rule BOQ?

A thumb-rule BOQ provides a preliminary quantity framework. Final quantities may vary slightly after detailed structural design and site conditions are confirmed.

Q. Can a contractor change the BOQ after construction starts?

Yes, but any modification should be documented and justified with revised measurements to maintain transparency.

Over to You

A residential building project involves multiple measurable components. When these components are clearly defined in advance, budgeting becomes more structured and transparent.

A construction BOQ does not replace structural drawings or detailed design. However, it provides a measurable framework that supports cost planning and contractor comparison.

In practice, most cost overruns in residential projects can be traced back to unclear quantities at the beginning. Preparing or reviewing a BOQ before execution reduces that uncertainty significantly.